Sriracha Construction Public Company Limited บริษัท ศรีราชาคอนสตรัคชั่น จำกัด (มหาชน) Facebook
         

1) CLIENT: CHIYODA CORPORATION
PROJECT: THAIOIL STAGE II EXPANSION PROJECT
LOCATION: THAIOIL REFINERY, SRIRACHA, CHONBURI
PERIOD: 1990
VALUE: 90,000,000 Bahts
STATUS: SUBCONTRACTOR
WORK SCOPE:
1. OFFICE - ONE STOREY CONSTRUCTION
2. WAREHOUSE - ONE STOREY CONSTRUCTION
3. SUPPLY OF LATERITE (EARTH FILL) MATERIALS

2) CLIENT: THAPPLINE
PROJECT: NONGJOK TERMINAL
LOCATION: NONGJOK POWER PLANT, NONGJOK, BANGKOK
PERIOD: FEB - JUN, 1995
VALUE 6,000,000 Bahts
STATUS: CONTRACTOR
WORK SCOPE:
1. CONTROL BUILDING - ONE STOREY
2. EQUIPMENT FOUNDATION
3. MISCELLANEOUS CIVIL WORK, PIPE SLEEPER

3) CLIENT: BP / Q8 CHONBURI TERMINAL
PROJECT: TERMINAL IMPROVEMENT

LOCATION: BP / Q8 CHONBURI TERMINAL, SRIRACHA, CHOLBURI
PERIOD: JUL - OCT 1995
VALUE: 2,800,000 Bahts
STATUS: CONTRACTOR
WORK SCOPE:
1. CONCRETE PAVEMENT
2. DEEP WEEL
3. GATE 10 M WIDTH
4. BRIDGE OVER PIPLINE
5. RC. GUTTER
6. PIPING WORK
7. CHAINLINK FENCE
8. BARBERED WIRE FENCE
9. MISCELLANEOUS WORK

4) CLIENT: CHIYODA
PROJECT: IT FORGING PLANT

LOCATION: SIAM EASTERN INDUSTRIAL PARK, PLUAKDAENG, RAYONG
PERIOD: 1995
VALUE 45,000,000 Bahts
STATUS: SUBCONTRACTOR
WORK SCOPE:
1. DRAINAGE GUTTER / PIPE
2. CONCRETE ROAD & YARD
3. EQUIPMENT FOUNDATION
4. SUBSTATION
5. CONCRETE WATER POND
6. BRICK FENCING
7. UNDER GROUND AND ABOVE GROUND PIPING WORK 21,000 IN-M

5) CLIENT: CHIYODA
PROJECT: HITACHI CHEMICAL AUTOMATIVE PROJECT (THAILAND )

LOCATION: SIAM EASTERN INDUSTRIAL PARK, PLUAKDAENG, RAYONG
PERIOD: 1996
VALUE: 51,000,000 Bahts
STATUS: SUBCONTRACTOR
WORK SCOPE:
1. PLANT BUILDING AND OFFICE
2. DRAINAGE / GUTTER
3. EQUIPMENT FOUNDATION
4. MINOR BUILDING
5. WATER POND
6. ROAD
7. FENCING

6) CLIENT: THAI POLYACETAL CO., LTD.
PROJECT: WASTE WATER TREATMENT FACILITIES
LOCATION: PADAENG INDUSTRIAL ESTATE, MAP TA PHUT, RAYONG
PERIOD: MAR, 1997
VALUE: 2,500,000 Bahts
STATUS: DESIGNER AND CONTRACTOR
WORK SCOPE:
1. WASTER WATER PIT
2. WASTE SHETER
3. SOLID WASTE INCINERATOR FOUNDATION
4. CONCRETE ROAD AND PAVEMENT
5. R.C. GUTTER AND MANHOLE
6. PUMP AND PIPING WORK

7) CLIENT: THAI CARBON PRODUCT CO., LTD.
PROJECT: ENCLOSURE OF MAIN BAG FILTER AND TOILET & LOCKER ROOM
LOCATION: AO UDOM, SRIRACHA, CHOLBURI
PERIOD: JUN - JUL, 1997
VALUE: 1,400,000 Bahts
STATUS: CONTRACTOR
WORK SCOPE:
1. METAL SHEET AND STEEL FRAME WORK
2. TOILET & LOCKER ROOM

8) CLIENT: HMT POLYSTYRENE CO., LTD.
PROJECT: 2nd FL. OFFICE REMODELLING

LOCATION: MAP TA PHUT INDUSTRIAL ESTATE, MAP TA PHUT, RAYONG
PERIOD: JUL - AUG 1997
VALUE: 3,200,000 Bahts
STATUS: DESIGNER AND CONTRACTOR
WORK SCOPE
1. INTERIOR DESIGN AND BUILD
2. AIR CONDITIONAL DUCT SYSTEM
3. ELECTRICAL AND LAN NETWORK SYSTEM
4. WAREHOUSE OFFICE EXTENSION

9) CLIENT: FOSTER WHEELER INTERNATION CORPORATION
PROJECT: SMALL POWER PLANT

LOCATION THAI OIL REFINERY, SRIRACHA, CHOBURI
PERIOD: AUG - NOV 1997
VALUE: 1,600,000 Bahts
STATUS: SUBCONTRACTOR
WORK SCOPE:
1. BATTERY ROOM
2. ANALYZER HOUSE
3. PUMP SUMP
4. PERMANENT FENCE AND GATE 200 M

10) CLIENT: JGC CORPORATION
PROJECT: THAI PARAXYLENE
LOCATION: AO UDOM , SRIRACHA, CHOBURI
PERIOD: JUL - DEC 1997
VALUE: 9,100,000 Bahts
STATUS: SUBCONTRACTOR
WORK SCOPE:
1. FOSTER WHEELER SITE OFFICE
2. JGC SITE OFFICE
3. TPX SITE OFFICE
4. JGC SITE WAREHOUSE
5. MISC. TEMPORARY FACILITIES

11) CLIENT: SRIRACHA YOKOYAMA CO., LTD.
PROJECT: WAREHOUSE AND OFFICE

LOCATION: SRIRACHA, CHOBURI
PERIOD: JAN - APR 1998
VALUE 6,500,000 Bahts
STATUS: CONTRACTOR
WORK SCOPE:
1. WAREHOUSE 12mW x 90mL x 9mH
2. OFFICE 6mW x 12mL x 4mH
3. RC DRAINAGE PIPE, GUTTER & MANHOLE
4. FENCE
5. RC YARD

12) CLIENT: THAI TAIHEI CO., LTD
PROJECT: COCO PHASE III HYBRID BLOCK 1 & 2

LOCATION: MAP TA PHUT INDUSTRIAL ESTATE, MAP TA PHUT, RAYONG
PERIOD: MAY 1997 - JUN 1999
VALUE: 300,000,000 Bahts ( Inclusive of Mechanical Work)
STATUS: SUBCONTRACTOR
WORK SCOPE:
1. THREE STOREY OF CONTROL BUILDING
2. TWO UNIT OF 3 STORY TURBINE BUILDING
3. TWO UNIT OF 14 STORY BOILER BUILDING
4. ASH SILO CONTROL BUILDING
5. CHLORINATION BUILDING

13) CLIENT: FOSTER WHEELER INTERNATIONAL CORPORATION
PROJECT: THAI AEROMATICS RECOVERY PROJECT (TARP) OF ESSO (THAILAND)
LOCATION: ESSO REFINERY , SRIRACHA, CHOLBURI
PERIOD: JUL 1998 - JUN 1999
VALUE: 10,000,000 Bahts
STATUS: CONTRACTOR
WORK SCOPE: PIPE SLEEPERS, PIPE

14) CLIENT : THAI CARBON PRODUCT CO., LTD
PROJECT FUEL OIL TANKS

LOCATION: AO UDOM, SRIRACHA, CHONBURI
PERIOD: JAN - FEB 1999
VALUE 2,000,000 Bahts
STATUS: CONTRACTOR
WORK SCOPE: 4 TANK FOUNDATION

15) CLIENT: BAYER POLYMERS CO., LTD
PROJECT: POLYCARBONATE PLANT

LOCATION: MAP TA PHUT, INDUSTRIAL ESTATE, MAP TA PHUT, RAYONG
PERIOD: JUN - DEC 1999
VALUE: 6,386,000 Bahts
STATUS: DESIGNER AND CONTRACTOR
WORK SCOPE:
1. TANK FOUNDATION
2. WAREHOUSE OFFICE REMODELLING 400 M2 (INTERIOR DESIGN, DECARATING , ELECTRICAL, AIR CONDITIONING, LAN AND OFFICE FURNITURE SUPPLY )
3. RC PAVEMENT
4. ARCHITECTURAL CLADDING 1250 M2
5. PC SILO PORCH 370 M2
6. UNDERGROUND 286 M OF PE. & 43 M OF PVC PIPE & BOX CULVERT
7. BUILD IN FURNITURE
8. CLEAN FOOM 3.5 mW X 4.3 mL X 3.5 mH
9. TANK PAINTING AND ART WORK

16) CLIENT: SRIRACHA GARAGE CO., LTD.
PROJECT GARAGE WORKSHOP AND OFFICE

LOCATION: SRIRACHA, CHONBURI
PERIOD NOV 1999 - MAR 2000
VALUE: 6,500,000 Bahts
STATUS: CONTRACTOR
WORK SCOPE:
1. WORKSHOP 12mW X 60mL X 8mH
2. WORKSHOP 8mW X 30mL X 4mH
3. OFFICE 8mW X 12mL X 4mH
4. STORE 6mW X 12mL X 4mH
5. WORKER’S TOILET 4mW X 6mL X 3mH
6. RC DRAINAGE PIPE, GUTTER & MANHOLE
7. FENCE
8. ASPHALTIC YARD
9. RETAINING WALL

17) CLIENT: THAI POLYCARBONATE CO., LTD.
PROJECT: POLYCARBONATE PLANT MODIFICATION
LOCATION PADAENG INDUSTRIAL ESTATE, MAP TA PHUT, RAYONG
PERIOD: JUL 1999 - MAY 2000
VALUE: 8,600,000 Bahts
STATUS: DESIGNER AND CONTRACTOR
WORK SCOPE:
1. SILO V-S70 FOUNDATION
2. BOOSTER PUMP FOUNDATION
3. COOLING TOWER (G-010B) FOUNDATION
4. TANK V-177 B FOUNDATION
5. RC ROAD 4,352 Sq.m.

18) CLIENT: MENU 10 PUB AND RESTAURANT
PROJECT: MENU 10 EXPANSION

LOCATION: PACIFIC PARK PLAZA, SRIRACHA, CHONBURI
PERIOD OCT - NOV 1999
VALUE: 1,500,000 Bahts
STATUS: DESIGNER AND CONTRACTOR
WORK SCOPE: DESIGN AND CONSTRUCTION OF TWO STORY RESTAURANT

19) CLIENT: LOMPA METALS CO., LTD.
PROJECT: NEW FACTORY

LOCATION: NONG KHAM, SRIRACHA, CHONBURI
PERIOD: SEP 1999 - FEB 2000
VALUE: 30,000,000 Bahts
STATUS: CONTRACTOR
WORK SCOPE:
1. PLANT BUILDING AND OFFICE
2. RC DRAINAGE PIPE, GUTTER & MANHOLE
3. FOUNDATION FOR 2 SETS OF HOLDING MACHINE TRUCK SCALE,
NITROGEN AND FUEL TANK
4. MINOR BUILDING SUCH AS CANTEEN, GUARDHOUSE, WORKER’S TOILET, & CAR PARKING SHED.
5. UNDERGROUND WATER TANK
6. RC PAVEMENT
7. RC WALL FOR RAW MATERIAL STOCK 5 mH X 150 mL
8. FENCING

20) CLIENT: THAI GYPSUM PRODUCTS CO., LTD.
PROJECT: STOCK YARD

LOCATION: LEAM CHABNG INDUSTRIAL ESTATE, SRIRACHA, CHOLBURI
PERIOD: APR - MAY 2000
VALUE: 3,800,000 Bahts
STATUS: DESIGNER AND CONTRACTOR
WORK SCOPE: RC STOCK YARD AND ROAD 6,640 Sq.m.

21) CLIENT: BAYER THAI CO.,LTD.
PROJECT: INFRASTRUCTURE OF PC II & BPA

LOCATION: MAP TA PHUT, INDUSTRIAL ESTAT , MAP TA PHUT, RAYONG
PERIOD: JUL. 2000 - PREESNT
VALUE: 120,000,000 Bahts
STATUS: DESIGNER AND CONTRACTOR
WORK SCOPE:
1. 4 BASING OF COOLING TOWER
2. 800 M LENGTH OF PIPERACK (1,000 TONS OF STEEL WEIGHT)
3. 6 CHILLER FOUNDATION AND SHELTER 275 M2
4. STORM DRAINAGE GUTTER
5. RC PAVEMENT
6. UNDERGROUND 12” FIRE WATER MAINLINE
7. TANK FOUNDATION
8. RC TANKS
9. DUCT BANK & CABLE TRENCH
10. 70 TONS TRANSFORMER FOUNDATION
11. SUBSTATION BUILDING
12. PIPE SLEEPERS
13. MISCELLANEOUS FOUNDATIONS

22) CLIENT: BPB THAI GYPSUM PRODUCT CO., LTD.
PROJECT: EXPANSION PROJECT
LOCATION: LEAMCHABANG INDUSTRIAL ESTATE, SRIRACHA
PERIOD: JUN 2004 - JUL 2005
VALUE: 200,000,000 Bahts
STATUS: DESIGN, PROCUREMENT & CONSTRUCTION
WORK SCOPE: MECHANICAL / CIVIL / BUILDING WORKS